Status: In Progress
Project Number: 22
Category: Multi-Use Path System
Location: Parallel to HWY 54 at Lake Peachtree
Proposed Project Year: 2019
Original Project Budget: $539,000
Project/Goal Description: Replace the existing single-lane multi-use path bridge with a 14’ wide multi-use path bridge to allow for two-way cart, bicycle, and pedestrian traffic.
December 2022 Progress Update: The City has contracted with a design-build contractor to perform the design and construction of this bridge. Currently, Public Works has received approval from the Georgia Department of Transportation (DOT) for a temporary path to be located on DOT right-of-way during construction. This now enables the designer to complete the analysis of alternatives for the City to review, to allow the bridge to be closed for up to 8 months during construction with a detour onto the shoulder of HWY 54. City Council approved to move forward with the construction portion of the project in December of 2022.
SPLOST Actuals Total: $2,075,923.97
SPLOST Funds Over/Under Budget: $(1,536,923.97)
Proposed Project Photo:

Proposed Project (60% Design Drawing):