2017 Project 21: New Path Connection – Kedron Village Retail Path Relocation

Status: Completed

Project Number: 21

Category: Multi-Use Path System

Location: Newgate Rd to Kedron Village Retail (by Ross)

Proposed Project Year: 2017

Project Budget: $18,185

Project/Goal Description: Relocate path currently emptying into rear entrance drive to the wider parking area in front of Ross.

2022 Progress Update: Public Works negotiated easements with the shopping center and constructed the path extension back to the access drive behind Ross. 

SPLOST Actuals Total: $3,146

SPLOST Funds Over/Under Budget: $15,039

Proposed Project Photo:Map

Description automatically generated

Final Project Photos: