2017 Project 20: New Path Connection – Police Station

Status: Completed

Project Number: 20

Category: Multi-Use Path System

Location: HWY 74 S

Proposed Project Year: 2019

Project Budget: $51,523

Project/Goal Description: New path connecting the Peachtree City Police Station to the path behind Sweetgum Rd.

2022 Progress Update:  Public Works procured the needed easements and constructed a new path connection from the Police Department’s access road through Water and Sewerage Authority property, sewer easements, and greenbelt into Briarwood Court. This alternate connection was chosen because of drainage concerns and environmental impacts. 

SPLOST Actuals Total: $20,366

SPLOST Funds Over/Under Budget: $31,157

Proposed Project Photo:

A picture containing text, electronics

Description automatically generated

Final Project Photos: