2017 Project 14: New Path Connection – Robinson Road (Whitfield Farms/Spear Road)

Status: Completed

Project Number: 14

Category: Multi-Use Path System

Location: Robinson Rd

Proposed Project Year: 2017

Original Project Budget: $132,000

Project/Goal Description: New path on Robinson Rd from Spear Rd to Whitfield Run.

2022 Progress Update: Public Works laid out and constructed this path project in 2018.  Public Works also extended the path further up to Woodland Drive providing for a safer crossing of Robinson Road in this area. 

 SPLOST Actuals Total:  $14,204

SPLOST Funds Over/Under Budget: $117,796

Proposed Project Photo:

A picture containing text, tree, outdoor

Description automatically generated

Final Project Photos: