Status: Completed
Project Number: 14
Category: Multi-Use Path System
Location: Robinson Rd
Proposed Project Year: 2017
Original Project Budget: $132,000
Project/Goal Description: New path on Robinson Rd from Spear Rd to Whitfield Run.
2022 Progress Update: Public Works laid out and constructed this path project in 2018. Public Works also extended the path further up to Woodland Drive providing for a safer crossing of Robinson Road in this area.
SPLOST Actuals Total: $14,204
SPLOST Funds Over/Under Budget: $117,796