2017 Project 10: New Path Connection – Peachtree Parkway N @ North Hill

Status: In Progress

Project Number: 10

Category: Multi-Use Path System

Location: N. Peachtree Pkwy

Proposed Project Year: 2023

Original Project Budget: $215,000

Project/Goal Description: New path to facilitate travel along the N. Peachtree Parkway between North Hill South and North Hill North

December 2023 Progress Update: Public Works has contracted out the surveying of the property lines and topography of this area and this has been completed.  Design of the path connection and drainage culverts is scheduled next. Peachtree City plans on completing this path connection in 2024 utilizing City Path crews.

SPLOST Actuals Total: $9,788.51

SPLOST Funds Remaining$205,211.49

Proposed Project Photo:

Map

Description automatically generated

Final Project Photos: N/A